Project Risk Analysis with Tornado Diagrams, Monte Carlo Simulation and the Value of Information
How spider plots, switching values, scenarios, decision trees, Monte Carlo and risk premiums show how far to trust a project’s NPV
Key takeaways
A positive NPV is a single point built on forecasts. Spider plots and tornado diagrams show which inputs move it most; switching values tell managers how wrong a forecast can be before the decision flips.
Safety margins computed one variable at a time do not add up: in the worked case, a 15% cash-flow shortfall and a 20% cost overrun are each "safe" alone but together turn the NPV negative.
The expected value of perfect information (EVPI) is only a ceiling. A real test market that can mislead must be valued with Bayes' theorem, and a study priced below EVPI can still be a bad buy.
Monte Carlo simulation handles many inputs at once, but ignoring the correlation between cost overruns and weak sales made the probability of loss look about a quarter smaller than it was.
Adding a risk premium to the MARR suits steady, economy-wide risk. It double-counts risk when cash flows are already pessimistic and penalizes long-lived projects far more than their real risk warrants.
Large projects around the world miss their numbers in a remarkably consistent direction. Studying hundreds of infrastructure and corporate projects, Flyvbjerg (2006) found that cost overruns and benefit shortfalls are the rule rather than the exception, and that the errors lean toward optimism far more often than chance would allow. Yet the investment proposals that start these projects usually present a single net present value (NPV), computed from a single forecast of each input, as if the future were already known.
Consider a small illustrative case. A fruit processor is weighing a compact freeze-drying line for mango and jackfruit snacks, to be sold to supermarket chains and export buyers. The estimated investment is $80,000, the expected net cash flow is $20,800 a year for 8 years, the line should fetch about $8,000 at the end of its life and the company's minimum attractive rate of return (MARR) is 12% a year. With (P/A, 12%, 8) = 4.9676 and (P/F, 12%, 8) = 0.4039, the net present value is NPV = −80,000 + 20,800 × 4.9676 + 8,000 × 0.4039 = $26,558. The figure is positive and comfortably large, so that is what the proposal to the board reports.
None of these inputs is a known fact. Is $80,000 a supplier's binding quote or a rough estimate? What volume, raw fruit price and exchange rate lie behind the $20,800 cash flow? Is eight years the technical life of the equipment or its economic life before a better technology arrives? Each question opens a range. Risk analysis does not change the $26,558; it tells the decision maker how much to trust it, which inputs must be pinned down before money is committed and whether it is worth paying to learn more first.
This article works through that question in ten sections. Section 1 separates uncertainty from risk. Section 2 presents one-variable sensitivity analysis through spider plots and tornado diagrams. Section 3 computes switching values and safety margins. Section 4 builds three consistent scenarios and computes the expected value and standard deviation. Section 5 estimates the probability of a loss. Section 6 uses a decision tree to price information, separating the value of perfect information from the value of a test that can be wrong. Section 7 runs a Monte Carlo simulation. Section 8 discusses when a risk premium in the MARR helps and when it misleads. Section 9 shows how to build the whole analysis in a spreadsheet and Section 10 collects the common mistakes.
1. Uncertainty and risk
This section separates two words that are often used interchangeably, because in project analysis they describe different levels of knowledge and call for different tools.
Uncertainty describes a variable that can take several values when we cannot assign a probability to each. Risk describes a variable whose probability distribution is known, or can be estimated on a sound basis. The distinction is usually traced to Knight (1921), who separated risk that can be measured by probabilities from uncertainty that cannot. Under uncertainty, the analyst relies on tools that need no probabilities, such as sensitivity analysis and switching values; once probabilities can be assigned, expected values, standard deviations, decision trees and simulation become available (Park, 2019).
Most business projects sit in the gray zone between the two, so both families of tools are usually needed. A common trap is to treat a probability guessed by an expert as if it had been measured from data: a figure of 0.25 looks as precise as any other number, so readers of the report cannot tell that the analysis is still in the territory of uncertainty. It also helps to separate parameter uncertainty, where the structure of the problem is known but the values of inputs such as next year's fruit price are not, from structural uncertainty, where the model itself may be wrong because an importing country changes its food safety rules or a much cheaper drying technology appears. The tools in this article handle the first kind well. The second kind can only be managed through flexible design, such as choosing a dryer that can process several fruits, combined with periodic reviews of the decision.
2. One-variable sensitivity analysis
Sensitivity analysis is the first tool analysts reach for and the most widely used. This section presents two ways to draw its results and the most important limit on what it can say.
The procedure is simple: vary one input at a time over a range, for example plus or minus 30%, hold every other input at its base value and record the NPV. The interesting part is not the arithmetic but how the results are read and presented so that the importance of several inputs can be compared at a glance.
2.1. Spider plots
A spider plot draws NPV as a function of the percentage change in each input, so every line passes through the base case. Figure 1 shows the plot for the freeze-drying line with five inputs: net annual cash flow A, investment P, MARR i, salvage value S and life n.

In Figure 1 the slope carries the message. The steeper a line, the more sensitive the NPV is to that input. The net cash flow line is the steepest and crosses zero when cash flow falls by about 25.7%; the salvage value line is nearly flat, so there is no point arguing about what the equipment will fetch in eight years. The MARR line curves slightly because i enters the denominator through a power, while the lines for A, P and S are perfectly straight because NPV is a linear function of each. Life must be a whole number of years, so it appears as separate points.
2.2. Tornado diagrams and labeling both ends of each bar
A tornado diagram presents the same information as horizontal bars. Each bar spans the NPV obtained as one input moves from its low level to its high level, and the bars are sorted from widest to narrowest, which gives the chart its funnel shape. Table 1 holds the data behind the diagram, with ranges of plus or minus 30% for A, P, S and i, and life rounded to 6 and 10 years.
The detail that needs care when Table 1 becomes a chart is the labeling of each bar's ends. For A, n and S, the low level of the input gives the low NPV; for P and i it is the other way round: the highest investment, $104,000, is the end that gives the lowest NPV, and the 8.4% MARR is the end that gives the highest. A chart that labels the left end "low" and the right end "high" for every bar will mislabel the bars for P and i, a mistake that automated charting tools make often. The safe practice is to write, at each end of each bar, the specific value of the input and the resulting NPV, as in Figure 2.

Figure 2 leads to a clear course of action. Net cash flow is the most critical input, with an NPV range of $61,996, and it is the only input that can push NPV below zero on its own within the plus or minus 30% band. Investment comes second: at $104,000 the project still earns only $2,558. Salvage value hardly matters. The project team should spend its effort firming up the revenue forecast (supermarket orders, export prices) and the investment estimate (a binding quote from the equipment supplier) rather than refining the resale price.
2.3. The limit of changing one input at a time
One-variable analysis holds every other input fixed, so it ignores the correlation between them. This subsection explains why that limit usually makes the picture look better than it is.
In practice, inputs rarely move independently. When the local currency weakens sharply, imported equipment costs more, so the investment exceeds its estimate; at the same time imported packaging costs more, so net cash flow falls. When consumer demand weakens, volume and price fall together. Inputs deteriorate together because they share a root cause, so the real risk is larger than the individual tornado bars suggest. Sensitivity analysis is therefore a screening step that identifies the inputs that matter, not the final word.
3. Switching values and safety margins
Sensitivity analysis asks how much NPV changes when an input changes. A switching value asks the reverse question: how bad must this input become before the decision flips? This section computes the switching value for each input and explains why the resulting safety margins cannot be added together.
The switching value of an input is the value that makes NPV equal to zero while the other inputs stay at their base values. For a uniform cash flow it can be solved directly: A* = [P − S × (P/F, i, n)] / (P/A, i, n) = (80,000 − 8,000 × 0.4039) / 4.9676 = $15,454 a year. Against the forecast of $20,800, net cash flow can fall by 25.7% before the project stops paying its way; that gap is the input's safety margin. Table 2 repeats the exercise for the other inputs.
The MARR row in Table 2 deserves attention: the discount rate that makes NPV equal to zero is the definition of the internal rate of return. In other words, the IRR is simply the switching value of the MARR. The same idea is used in public cost-benefit analysis to find the level of benefits or capital cost that brings a benefit-cost ratio down to 1.
The strength of switching values is that they express uncertainty in terms managers can judge. "NPV is sensitive to cash flow" is abstract; "net cash flow must fall short by more than a quarter before the project stops paying" is a statement a sales director can test against experience. Translating it into revenue takes one more step: if operating costs stay fixed, every dollar of lost revenue comes straight out of net cash flow. With revenue of $52,000 a year, the $5,346 cash-flow shortfall corresponds to a revenue drop of only about 10.3%.
The limit of this tool is that each switching value assumes every other input stays put, so the safety margins do not add up. If cash flow falls 15% and the investment overruns by 20% at the same time, each input stays well within its own margin, yet the NPV becomes −96,000 + 17,680 × 4.9676 + 8,000 × 0.4039 = −$4,941, and the project loses money.
4. Scenario analysis
To overcome the main weakness of one-variable analysis, scenario analysis changes several inputs at once in combinations that make sense together. This section builds three scenarios and then computes the expected value, standard deviation and coefficient of variation.
4.1. Scenarios must be internally consistent
A pessimistic scenario is not built by mechanically taking the worst value of every input; doing so with A = $14,560, P = $104,000, n = 6 and S = $5,600 gives an NPV of −$41,301, a future that is almost impossible. A credible scenario tells a story: the currency weakens sharply, so the investment rises to $96,000; at the same time demand softens and export orders stall, so net cash flow is only $15,200; and a new generation of drying technology means the line stays competitive for only 6 years. The optimistic scenario is built the same way: a long-term contract with a large supermarket chain, a discount from the equipment supplier and a line that runs for 9 years. Table 3 sets out the three scenarios, with the MARR held at 12% and salvage value at $8,000.
4.2. Expected value, standard deviation and coefficient of variation
The expected value is the probability-weighted average of the outcomes: E(NPV) is the sum of p_k × NPV_k. For Table 3, E(NPV) = 0.25 × (−29,454) + 0.50 × 26,558 + 0.25 × 65,288 = $22,238, about $4,320 below the base case, because the pessimistic scenario loses more than the optimistic scenario gains.
The expected value on its own says nothing about dispersion. The standard measure of dispersion is the standard deviation: σ² = 0.25 × (−29,454 − 22,238)² + 0.50 × (26,558 − 22,238)² + 0.25 × (65,288 − 22,238)² ≈ 1.141 billion, so σ ≈ $33,774. To compare projects of different sizes, the coefficient of variation is used: CV = σ / E(NPV) = 33,774 / 22,238 = 1.52. A dispersion larger than the expected value itself signals high risk: the project is worth doing on expectation, but the company has to ask whether it can absorb a loss of nearly $30,000 if the pessimistic scenario occurs (Newnan et al., 2020). The coefficient of variation loses its meaning when the expected value is close to zero or negative; in that case, report σ directly together with the probability of a loss.
5. Estimating the probability of a loss
Decision makers often want a simpler number: what is the chance that the project loses money? This section presents an estimate based on the normal distribution and three limits that must be stated whenever it is used.
If NPV is assumed to be roughly normally distributed, the zero point can be standardized: z = (0 − E) / σ = (0 − 22,238) / 33,774 = −0.66. The probability that NPV is below zero is the area of the standard normal distribution to the left of z, about 25.5%; the spreadsheet function NORM.DIST(0, 22238, 33774, TRUE) gives the same result. Put simply, the project has about a one-in-four chance of losing money.
The number has three limits. First, the normal distribution is only an approximation, and a rough one here because there are only three discrete scenarios: if the three-scenario model is taken literally, the probability of a loss is exactly the probability of the pessimistic scenario, 25%, and the closeness of the two numbers is a coincidence. Second, the probabilities of 0.25 and 0.50 are subjective judgments: if the pessimistic scenario had a probability of 0.35 and the optimistic one 0.15, the expected value would drop to $12,763. Third, "a 25.5% probability of loss" sounds far more scientific than it is. The honest presentation states the number together with its assumptions and shows what happens when those subjective probabilities are changed.
6. Decision trees and the value of information
A decision tree compares multi-step strategies in which later choices depend on information gathered earlier. This section uses a tree to answer a very practical question for a capital project: is it worth paying to learn more before investing, and if so, how much?
6.1. Perfect information and EVPI
A tree has two kinds of nodes. At a decision node, drawn as a square, the company picks the branch with the best expected value. At a chance node, drawn as a circle, the market decides, so the analyst takes a probability-weighted average. The tree is solved backward from the tips to the root. The fruit processor has three options: invest now, with an expected value of $22,238; do not invest; or spend $2,400 on a market study first and decide afterward. Figure 3 draws the tree under the temporary assumption that the study reveals with certainty which state the market will be in.

Following Figure 3, if the study reports a strong market, the company invests and earns $65,288; if it reports the base market, the company invests and earns $26,558; if it reports a weak market, the company stays out and receives $0 instead of losing $29,454. The expected value with advance knowledge is 0.25 × 65,288 + 0.50 × 26,558 + 0.25 × 0 = $29,601.
Two numbers need to be kept apart. The difference 29,601 − 22,238 = $7,363 is the expected value of perfect information (EVPI): the most the company should pay for any source of information about the state of the market, because no source can beat knowing for certain. The figure of $4,963 is something else: the net gain of the study strategy over investing now, equal to EVPI minus the $2,400 fee, and valid only if the study is truly perfect. Confusing $4,963 with EVPI confuses "the price ceiling for information" with "the profit left after paying for it". Notice also that information does not make the project better; it only helps avoid the bad branch. Here EVPI is exactly 0.25 × 29,454, the loss in the pessimistic scenario times its probability. For a capital project this is the typical shape of the value of information: it is the expected loss that a timely "no" would have prevented.
6.2. Imperfect information: small and large test markets
No study reveals the future with certainty. This subsection prices a test that can be wrong, using the expected value of sample information (EVSI) obtained through Bayes' theorem, and focuses on what the result means for the investment decision.
Suppose that for $2,400 the company can sell the product through two supermarket chains for three months. The result is reported only as "favorable" or "poor" and can be wrong. A small test reports "poor" with probability 0.8 when the market is really weak, 0.2 when it is at the base level and 0.1 when it is strong. The probability of a "poor" report is 0.25 × 0.8 + 0.50 × 0.2 + 0.25 × 0.1 = 0.325. By Bayes' theorem, after a "poor" report the probability of a weak market rises from 0.25 to 0.2 / 0.325 = 0.615, the base market falls to 0.308 and the strong market to 0.077; the expected NPV under these revised probabilities is −$4,931, so the company does not invest. After a "favorable" report (probability 0.675), the expected NPV is $35,319, so it invests. The expected value of the test strategy before the fee is 0.675 × 35,319 = $23,840, so EVSI = 23,840 − 22,238 = $1,603. Table 4 places this option beside a larger, more accurate test and beside perfect information.
Table 4 shows why EVPI must not be used as the value of a specific study. For the same project, with the same $2,400 fee and an EVPI of $7,363, the small test is worth only $1,603, so the company would pay $2,400 for something worth $1,603; the large test, which misleads less often, is worth $4,483 and is the only profitable purchase. Claiming that "the study is worth $4,963" without asking how accurate it is takes the most optimistic upper bound as the real number.
6.3. Three practical rules
The two subsections above yield three rules that apply whenever a team debates paying for market research, a technical pilot or a consultant's report. This subsection states them.
First, the information most worth buying is information that could change the decision, usually information about the bad scenario; if the company would act the same way whatever the study says, the information is worth nothing. Second, EVPI is an upper bound for quick screening: any study priced above $7,363 should be rejected without further calculation. Third, for a study priced below EVPI, estimate its accuracy and compute EVSI as in Table 4; that accuracy should come from earlier test markets or from the research provider's track record, not from numbers chosen to make the case look good.
7. Monte Carlo simulation
Monte Carlo simulation extends scenario analysis: each input is given a probability distribution, thousands of combinations are drawn at random, the NPV is computed for each and the results form a distribution. Hertz (1979) was among the first to bring this approach into corporate capital budgeting. This section runs a simulation for the freeze-drying line and reads the results.
7.1. Specifying distributions and correlation
The simulation uses 10,000 draws with a fixed random seed (seed 157 in NumPy's default generator) so that anyone who reruns it gets the same numbers. Net cash flow A follows a triangular distribution with a minimum of $15,200, a most likely value of $20,800 and a maximum of $25,600 a year; investment P follows a triangular distribution of $74,000, $80,000 and $96,000, skewed toward overruns; life takes the values 6, 7, 8 and 9 years with probabilities 0.2, 0.2, 0.4 and 0.2. Salvage value stays at $8,000 and the MARR at 12%. To reflect a shared root cause such as a currency shock, the simulation specifies a correlation of −0.6 between A and P: when the investment overruns, cash flow also tends to be low. The simulation is then run again with A and P independent to see what this assumption does. Figure 4 compares the two NPV distributions.

7.2. Reading the simulation results
With correlation, Figure 4 shows a mean NPV of $18,487, a standard deviation of $15,783 and a probability of loss of 13.0%; the worst 5% of draws give an NPV below −$7,995 and the best 5% give more than $44,425. When A and P are treated as independent, the mean barely moves ($18,476), but the distribution narrows, the standard deviation falls to $13,916 and the probability of loss drops to 9.6%. Ignoring correlation leaves the expected value intact but makes the probability of loss look about a quarter smaller, exactly the hidden optimism described in Section 2.3.
Three further points are worth recording. The mean NPV of $18,487 is below the base-case figure of $26,558 because the distributions lean toward the bad side: the average investment is about $83,333 rather than $80,000, and the average life is 7.6 years rather than 8. The base case in the proposal is therefore the "most likely" figure, not the expected one. The loss probability of about 13% is also far below the 25% of the three-scenario model, because that model places a quarter of the probability on a world where every input is bad at once, whereas the simulation lets inputs be partly bad and offset one another; the two numbers differ because the two sets of assumptions differ. Finally, the simulation result has its own error: with 10,000 draws the standard error of the loss probability is about 0.34 percentage points, and rerunning with 200 seeds (1 to 200) gave values between 12.2% and 14.0%, so the report should say "about 13%".
Simulation handles many inputs at once and can include correlation, precisely where one-variable analysis is weak. But its results are only as good as the distributions fed into it, and choosing those distributions usually rests on judgment; a chart built from ten thousand points easily creates a sense of precision far beyond the quality of the inputs. Flyvbjerg (2006) showed that real projects overrun costs and fall short on benefits systematically because of optimism bias, so self-specified distributions should be checked against the actual outcomes of similar completed projects, an approach he calls reference class forecasting.
8. Adjusting the MARR for risk
A very common way to handle risk is to add a risk premium to the MARR: riskier projects are discounted at a higher rate. This section discusses when that practice is sound and when it penalizes the wrong thing.
8.1. When a risk premium makes sense
The practice has a sound basis: investors demand higher returns to accept greater risk, so it is reasonable for a project that opens a new market to face a higher MARR than a routine equipment replacement (Sullivan et al., 2019). It fits when three conditions hold together: the cash flows used are expected values, not cash flows deliberately trimmed "to be safe"; the risk is tied to movements in the wider economy, as when revenue follows the business cycle; and the risk persists steadily throughout the project's life. For the freeze-drying line, adding 3 percentage points and discounting at 15% lowers NPV from $26,558 to $15,952; adding 5 points, at 17%, leaves $9,787, still positive. Companies should set premiums by project category in their investment policy in advance, rather than choosing a premium after seeing the result.
8.2. When a risk premium misleads
The first trap is counting the same risk twice. If the project team has already used the pessimistic cash flow of $15,200 a year instead of the expected value and then also discounts at 15%, the same risk is penalized twice: NPV is −$9,177, while the same pessimistic cash flow at the 12% MARR gives only −$1,261. The second trap is subtler: a fixed, higher discount rate penalizes distant cash flows exponentially more than near ones, even though the real risk may not grow that way. Figure 5 plots the share of a dollar's present value retained in each year when discounting at 15% or 17% instead of 12%.

As Figure 5 shows, a 3-point premium removes only about 3% of the value of a year-1 cash flow but 23% in year 10, 41% in year 20 and 55% in year 30; with a 5-point premium, a year-30 cash flow keeps only 27% of its value. If the main risks are concentrated early, such as construction cost overruns, permitting delays or commissioning that falls short of rated capacity, a fixed premium both penalizes the truly risky phase too lightly and penalizes the stable operating years too heavily. The practice is therefore systematically biased against long-lived projects such as water treatment plants, forestry or research and development, the same problem that arises when choosing a social discount rate for public investments.
The general principle is not to pack every worry into a single discount rate. When the risks can be described, use expected cash flows with the MARR for the project category and analyze risk explicitly through sensitivity, scenarios, decision trees or simulation (Blank & Tarquin, 2024). A risk premium suits steady background risk; project-specific risk, one-off risk and risk that can be reduced by buying information should be modeled separately.
9. Building the analysis in a spreadsheet
A spreadsheet is enough for every analysis in this article, provided each parameter sits in its own input cell and each result is a formula referring to those cells. This section presents a template.
Three Excel features are worth using: Goal Seek to find switching values, Data Table to build sensitivity tables and repeat a simulation, plus the RAND and NORM.S.INV functions to draw random numbers (Microsoft, n.d.). Table 5 lists the main cells.
The trick in the last rows of Table 5 is a Data Table whose input cell is an empty cell: each row of the table forces the spreadsheet to recalculate the whole model, which means drawing a fresh set of random numbers. Because the results change every time F9 is pressed, they must be pasted as values before being reported; the LET function requires Excel 365 or Excel 2021. Google Sheets has no Data Table, but the formulas can simply be copied down 10,000 rows. When an AI assistant that can run code builds the simulation for you, ask it to print the code, the distributions, the correlation coefficient and the random seed, then check at least the base case against your own spreadsheet.
10. Common mistakes
Risk analysis tools are not mathematically hard, but they are easy to misuse. This section gathers the mistakes encountered in the article; Table 6 lists them with ways to avoid them.
Most of the mistakes in Table 6 share one root: turning a subjective number into one that looks objective, or counting the same risk twice. Before presenting results, ask where each probability came from, whether the inputs could worsen together for one reason, whether risk already sits in the cash flows or in the discount rate and whether the information you plan to buy could actually change the decision.
Conclusion
Every input to a project is a forecast, so the goal of risk analysis is not to eliminate uncertainty but to know where it lies and how large it is. Sensitivity analysis and tornado diagrams identify the critical inputs, which for the freeze-drying line are net cash flow and investment. Switching values turn that sensitivity into safety margins that managers can judge: cash flow must fall short by more than 25.7%, or the investment must overrun by more than 33.2%, before the project stops paying, and the IRR is simply the switching value of the MARR. Because safety margins do not add up, the analysis also needs consistent scenarios, expected values, standard deviations, the probability of a loss and a simulation that includes correlation. Each tool gives a different number because it rests on different assumptions, so the assumptions must be written down beside the number.
A decision tree answers whether more information is worth buying. EVPI, here $7,363, is the price ceiling for any source of information; the net gain of $4,963 holds only if the study is perfect, while a test market that can mislead must be valued through EVSI and Bayes' theorem and may not be worth its fee even when that fee is below EVPI. A risk premium in the MARR suits steady background risk applied to expected cash flows, but it double-counts when cash flows are already pessimistic and weighs too heavily on long-lived projects. The same tools carry over to public investment and public-private partnerships, where the further question is not only how large the risk is but who should bear it.
References
Blank, L. T., & Tarquin, A. (2024). Engineering economy (9th ed.). McGraw Hill. https://www.mheducation.com/highered/product/engineering-economy-blank-tarquin/M9781264158096.html
Flyvbjerg, B. (2006). From Nobel Prize to project management: Getting risks right. Project Management Journal, 37(3), 5–15. https://doi.org/10.1177/875697280603700302
Hertz, D. B. (1979). Risk analysis in capital investment. Harvard Business Review, 57(5), 169–181. https://hbr.org/1979/09/risk-analysis-in-capital-investment
Knight, F. H. (1921). Risk, uncertainty and profit. Houghton Mifflin. https://oll.libertyfund.org/titles/knight-risk-uncertainty-and-profit
Microsoft. (n.d.). Calculate multiple results by using a data table. Microsoft Support. https://support.microsoft.com/en-us/office/calculate-multiple-results-by-using-a-data-table-e95e2487-6ca6-4413-ad12-77542a5ea50b
Newnan, D. G., Eschenbach, T. G., Lavelle, J. P., & Lewis, N. A. (2020). Engineering economic analysis (14th ed.). Oxford University Press. https://global.oup.com/ushe/product/engineering-economic-analysis-9780190931919
Park, C. S. (2019). Fundamentals of engineering economics (4th ed., Global ed.). Pearson. https://www.pearson.com/en-gb/subject-catalog/p/fundamentals-of-engineering-economics-global-edition/P200000005189
Sullivan, W. G., Wicks, E. M., & Koelling, C. P. (2019). Engineering economy (17th ed., Global ed.). Pearson. https://www.pearson.com/en-gb/subject-catalog/p/engineering-economy-global-edition/P200000005519/9781292264905